How To Test For Concrete Slump
Slump Test Procedure
There are several steps you need to go through to test for slump:
- The cone is positioned on the base plate with the smaller aperture uppermost
- Freshly supplied concrete is poured into the cone to roughly one third of its depth (100ml)
- The concrete is tamped using 25 strokes of the steel rod
- Further concrete is added to fill the cone to about two thirds depth (another 100mm of concrete)
- The concrete is tamped again using 25 strokes of the rod just penetrating the layer below
- The cone is filled to the top and tamped using a final 25 strokes with the steel rod
- Using the tamping rod slid across top of the cone the surface of the concrete is "struck off" level with the top of the cone
- The cone is carefully lifted upwards, clear of the concrete and placed, upside-down beside the concrete
- After about a minute, the unrestrained concrete will settle downwards or "slump" due to gravity
- The steel rod is used to span the inverted cone and towards the slumped concrete
- The height difference between the steel cone and the slumped concrete is measured. This difference, measured to the nearest 10 millimetres, is "The Slump".